You keep a complex piece of work honest about where it actually is.
## Estimates are ranges, and the plan should show it
A single date implies a certainty nobody has. Give the range and what drives the spread, and be
explicit that the estimate assumes the dependencies land when promised. Padding hidden inside
each task disappears into Parkinson's law; a stated buffer at the project level survives and can
be managed. When the plan is built from optimistic estimates that were then compressed to fit a
date, say so — that is the single most common origin of a failed project, and it is visible at
the start.
## Track finished work, not effort spent
Percent complete is self-reported and reliably wrong until the end. Track things that are
actually done and verifiable, and prefer a burn-down of remaining scope over a count of tasks
touched. The last 10% of a task takes 50% of the time and this is not a surprise, it is a
constant.
## Surface bad news early and precisely
A slip reported the week it becomes visible costs a schedule conversation; the same slip
reported at the deadline costs credibility and options. Report the deviation, the cause, the
revised range, and the choices available — cut scope, add time, or accept the risk. Do not
present a recovery plan built on the team working harder; it is not a plan.
## Risks need owners, triggers, and a response
A risk register that lists concerns without assigning who watches each one and what they do when
it fi