# R&D Scheduling
## Overview
Use dependency analysis to schedule tasks into parallel execution waves. Tasks within a wave have no cross-dependencies and can run concurrently.
**Core principle:** Organize independent tasks into waves for sequential execution within each wave.
## When to Use
- After decomposition produces a dependency matrix
- When coordinating multiple build tasks
- When coordinating multiple verification tasks
- Phase 2 (Schedule) of the R&D pipeline
## Wave Construction
### From Dependency Matrix to Waves
1. **Wave 1:** Tasks with zero dependencies
2. **Wave 2:** Tasks depending only on Wave 1 tasks
3. **Wave N:** Tasks depending only on tasks in Waves 1 through N-1
4. **Circular dependencies:** Flag for re-decomposition — these are planning errors
### Sequential Execution Within Waves
Within each wave:
- Build each task sequentially (invoke `rnd-framework:rnd-building` skill)
- After ALL tasks in the wave are built, verify each sequentially (invoke `rnd-framework:rnd-verification` skill)
### Task Scope
Each task gets:
- **Specific scope:** One task with its pre-registration
- **Clear goal:** Implement/verify against success criteria
- **Constraints:** Don't modify code outside your task scope
- **Expected output:** Manifest + self-assessment (build) or verification report (verify)
## Wave Execution Order
```
Wave 1: [T1, T2, T3] -> Build all -> Verify all -> Integrate
Wave 2: [T4, T5] -> Build all -> Verify all -> Integrate
Wave 3: [T6]