# Egret workflow
Start with the cheapest model that can answer the question. Do not jump into unit commitment when a single-snapshot OPF will do.
## Default tool ladder
1. `solve_dc_opf(case_file, solver, return_results)` for fast feasibility and congestion screening.
2. `solve_ac_opf(case_file, solver, return_results)` when voltage or reactive realism matters.
3. `solve_unit_commitment_problem(case_file, solver, mipgap, timelimit)` only after the horizon, reserve logic, and commitment assumptions are clear.
## Working rules
- Confirm the case file format, solver, and time horizon before solving.
- Use DC OPF first unless the question explicitly depends on AC feasibility.
- Treat UC as a higher-cost study that needs a clear operational objective.
- Hand off to `operations-planning-mitigation` when the solution is infeasible, too expensive, reserve-deficient, or overly curtailed.
- Validate promising dispatch fixes in an AC tool when voltage limits matter.
## Deliver
- The case, solver, and study type.
- The limiting constraints or binding tradeoffs.
- Whether the next step is AC validation, UC escalation, or mitigation.